Item Location Problem Date Reported Status
24 35 Lexington Rd. Window Sills rotting. Questioning who is responsible 6/30/03  
18 38 Lexington Rd Water problem in basement laundry room reported.  6/22/03 Glen has asked McNamara to look at situation as well as 45 Lexington
23 24 Lexington Rd Potential water problem around master bedroom windows - windowsills rotting from moisture and dampness 6/23/03  
20 35 Lexington piece of siding missing on the upper corner between 35 and 36 Lexington.  It looks like a place where the old gutter was.  Is this supposed to be covered? 6/19/03 Will be assessed
2 5 Lexington Water running down between gutter and fascia board 3/8/03 Not scheduled
4 Water Storage Facility Will not hold water   In process - Dec 2003 update
9 Many locations Touch-up paint primarily garage doors and trim 3/15/03 only open item is the cracked siding on the rear of unit
21 9 Village Green

6/22/03

Siding ripped to left of back door on deck since moved in
Wood frame to back door split where screen door attaches

Situation was assessed on 6/23/03.  The door frame damage was caused by the incorrect installation of the screen/storm door.  The door check which stops the door from swinging to far is screwed into the door frame with 1" screws instead of 21/2" to 3" screws.  The shorter screws only screw into the trim which is not strong enough to take the weight of the door when blown by the wind.  The longer screws screw into the 2"x4" frame which is much stronger.  PRVA is not responsible for the installation of the door.

Completed Maintenance Items

28b 43 Lexington Rd. The wood frame around the front door is rotten this was noticed when the owner attempted to install a new storm door. 8/2003 repaired Dec 2003 
10 Electrical power panels

All electrical power panels will be inspected. Those that fail the inspection will be repaired or replaced

The first electrical panels (electric meters) has been installed (9/10 Village Green).   The electrician has inspected most panels. Most passed inspection. Will be reviewed periodically.

51-52 meter panels replaced 9/03. 43 Lexington scheduled to be replaced 12/03.

15 1 Meetinghouse Large pot hole in driveway 4/22 New Driveway - COMPLETED
5 Corner at Meetinghouse/Bunker Hill Light Standard loose, broken below ground

 

8/1/02 COMPLETED 
22 9 Village Green Water leaking into attic 6/23/03 COMPLETED
13 45 Lexington Water in basement 3/31/03 COMPLETED
14 Mail Building Lettering still needs to be installed on the new awning at the mailbox area.  Corrective action regarding the mounted to the building is also needed.   1/03 COMPLETED

 

8 17 Lexington Rd water leak, siding requires caulking   COMPLETED
17 11MH 

 

 

 

bees nest behind front light between the brick facade and the light. Light will need to come down to kill the bees. 5/21/03 COMPLETED
27 5 Meetinghouse During the recent rains, noticed a leak in front bedroom. Specifically, small stain where the ceiling meets the wall, also horizontal water mark on the front wall, running between the two windows, half-way up. 8/7/03  COMPLETED

 

26 8 Meetinghouse
Water stains in the master bedroom ceiling 
8/6/03 COMPLETED
25 25 Lexington
Leaking around the vent fan in the full bath on the second floor.  
8/2/03 COMPLETED
28 43 Lex Water in the basement, this is caused by a crack in the foundation and the amount of rain.  8/2003 COMPLETED - Crack in foundation repaired
  13 Lex The carpet in the basement bedroom is wet. No viewable crack in the foundation but the ground at the back of the building is mud  8/2003 COMPLETED
7 Corner Lexington/Bunker Hill STOP sign needs replacing 8/1/02 COMPLETED
14 Mail Building Lighting situation  1/03

 COMPLETED

  3 Concord Trim around octagon window needs fixing   COMPLETED
1 25 Lexington Trim around octagon window missing 2/10/03 COMPLETED
19 15-18 Lexington No water is flowing from the inside rear gutter downspouts on 15-18 Lexington. The water is flowing over the end of the gutter onto the decks of 15-16 (esp 16).

rear gutter - Water is flowing between the gutter and building at the end near the bathroom of 18 Lex.

6/14/03

Completed 7/15

6 Many locations Faded NO PARKING signs 6/1/02 Completed 5/30/03
16 All buildings downspout extensions on the new front gutters with splash plates to prevent erosion   Completed 5/03/03
11 1 Concord Guard rail is broken 3/15/03 Completed 5/19/03
3 3 Lexington Deck/building flashing required and gutter repair 1/1/03 Completed 4/5/03
12 58 Lexington Missing roof vent 3/20/03 Completed 4/1/03

6D Certificates, Articles, Association Resources, Buyer and Seller Tools, Children and issues, Condo Fees, Decks, FAQs, Feedback Form, Fun Page, Ground News, Guest Book, Handyman Tips, Historical, Insurance, Mailbox info, Map, Master Deed, By-Laws, Mortgage Info, Newsletters, Objectives of this site, Opt-In Form, Outside Water Faucet, Parking, Pests , Pet Community, Picture Gallery, PRV Tidbits, Recycling, Trash, Roofs, Rules, Regulations, Statistics , Smoke Detectors, Snow, Ice, Steps, Salt, Stoves, Vendors, Wood
CAI member logo

Site designed and maintained by Michelle Fontaine (to email, please replace  AT with @
 this method keeps the automatic spam away)

 Email is fontaine15 AT charter.net 

To reach the BOARD by email , use 'Board AT paulreverevillage.com' (replace the AT  with @
 This method keeps the automatic spam away ) tel: (508) 581-9531